Regulations for Sewerage connection

 
Categories of sewer connections

Procedure for Sewer Connections

For getting new sewer connection

1.

Request for application in plain paper has to be submitted by the applicant  through the Licensed plumbers to the concerned Sub Division Officer.

    2

 

The application form duly filled up by the customer is to be submitted to the concerned Assistant       Executive Engineer. The ownership certificate from the local body/copy of building permit, copy of  permit of inside installation, three copies of plumbing plan prepared by a licensed plumber of  KWA and necessary postage stamps affixed in the acknowledgement cards should be submitted with the application. 
3.

After preliminary scrutiny at the subdivision the receipt of the application will be registered and an acknowledgement and intimation will be sent to the applicant.

4.

The application is then forwarded to the concerned Assistant Engineer for feasibility report.

5.

The Assistant Engineer after conducting site visit will submit the application to the  Assistant Executive Engineer with the feasibility report and observations if any. If more than one kitchen in a residential building/complex (in 1st floor, 2nd floor etc.), it will be treated as separate domestic connections.

 

6.

The feasible applications, which does not require any clearance from other departments (PWD, NH, Local bodies etc.), will be given a temporary sanction within a week and the applicant will be asked to execute an agreement in Rs. 50/- stamp paper. The customer, then has to remit the deposit and fees for the sewer connection. For others, the applicant has to produce the required clearance from other departments (consent/tar cut sanction from Local Body/PWD/NH if the line crosses public road after realising the restoration charges from the applicant there), and the time limit  will be one week after getting such clearance.  

7

After remitting the required fee, necessary work order for the connection is given from the sub division and the application forwarded to the Assistant Engineer for further action. 

8

The applicant has to give the completion report (inside installations and  connected work) through  the plumber. The connection shall be given after verification of the plumbing work. The maximum validity of the work order is six months. 

Fee for sewer connection and related services 

Application fee

 

Sl

Category

 Fee 

1 Residential houses, Non-domestic and Industrial (new) sewer connections   50   
2 Residential flats, residential complexes like colonies (new) 200   
3 For repairs, Alterations etc. 50   
4 For category conversion  50   
5 For Disconnection/Reconnection  50   

Connection fee and Security Deposit

 

    

Sl.

Category

Connection   Fee 

2Security    Deposit 

1 Domestic connection

10% of the estimate cost - minimum Rs. 500/-

500/-   

2 Non-domestic       " 10% of the estimate cost - minimum Rs.1000/-

1000/-   

3 Casual                  " 10% of the estimate cost - minimum Rs.1000/- 2500/-   

4

Industrial              " 10% of the estimate cost - minimum Rs.2500/- 3000/-   

  

2 Will be released as and when consumer stops the connection for ever.

 

     At  present no further charges (monthly or annually) are

 

Fee for Repairs/Alterations/Disconnection/Reconnection

 

 

Sl.No Category Fees
1 Repairs/Alteration 10% of estimated cost - minimum of Rs.100/-
2 Disconnection Rs.200/- in all cases
3 Reconnection  Rs.100/- in all cases

 

 

 

Change of Ownership

 

 

 

 

 

 

Sl

     Category

 Fee (Rs.)

1 Ownership change       100/-
2        "              in case of legal heirs - domestic            50/-  
3        "              for  residential complex / flat type         150/-

 